Six preparations before powering on and starting a frequency converter
a. Check whether the main power input and output wiring is correct and reliable. Ensure that the power voltage level meets the requirements specified in the SKI600 manual, and that all connections are secure. Inspect the insulation layer for any damage. Carefully check if the terminal blocks are loose or have potential short-circuit risks. Confirm that grounding is properly done.
c. Clean up any debris inside the VFD cabinet and recheck whether the main power cables, control wiring, ground wires, and neutral lines are properly connected. Keep the equipment environment clean and dry. Do not place any items near the SKI600. Carefully check for missing screws or wires to prevent small metal objects from causing a short circuit in the SKI600.
2. Review the customer's system control requirements and pipeline pressure settings. These must be recorded in detail.
3. Determine whether the VFD cabinet controls a submersible pump. For submersible pump motors, collect and confirm the following parameters: rated power, rated speed, and rated current. Consult with the customer to confirm these values and record them accordingly. If the VFD controls a centrifugal pump or fan, record the motor nameplate data so that accurate motor parameters can be entered into the SKI600 program, ensuring precise protection and control by the SKI600.
4. Check whether the customer’s pipeline installation and connections comply with our installation drawings. If the customer has not followed our installation guidelines, pay special attention to the installation positions of the check valve and measuring instruments. We must clearly inform the customer about the consequences of improper installation:
- Firstly, if a deep well submersible pump uses a control method without installing a check valve, water in the pipeline may flow back into the well when the pump stops, resulting in wasted electrical energy.
- Secondly, reverse operation of the submersible pump is strictly prohibited. Water backflow can cause the pump to run in reverse, often leading to loosening of internal fasteners and mechanical failure.
- Thirdly, since our water supply pipeline is a fully enclosed system, water returning to the well during shutdown can create a near-vacuum state within the pipeline. This vacuum negative pressure can damage the pressure measuring instruments installed on the pipeline due to suction effects, which may result in equipment failure on our side.
- The red wire of the shielded cable connects to the red output wire of the instrument,
- The yellow wire connects to the yellow output wire,
- The green wire connects to the blue output wire.
- Red shielded wire connects to the negative feedback terminal (–),
- Yellow shielded wire connects to the positive feedback input terminal (+),
- Green shielded wire connects to the internal feedback power terminal.
Sunye Electric owns independent intellectual property rights, with products certified by national authorities and multiple software copyrights and IP certificates. Significant investment is made annually in new technologies and product development, with numerous patents and software copyrights approved. The company possesses core platform technologies such as construction hoist drivers, high-performance vector inverters, servos, and permanent magnet synchronous motor controls. Medium- and low-voltage inverters and servo drives are widely used in industries such as lifting, stone processing, HVAC, machine tools, metal products, wire and cable, plastics, printing and packaging, textile and chemical fibers, building materials, metallurgy, coal mining, municipal services, and automotive manufacturing. Guided by the philosophy of “Innovation, Technology, Strength,” driven by the corporate spirit of “Unity, Progress, Pragmatism, Innovation,” and adhering to the business principle of “Sincerity and Excellence, Mutual Benefit and Coexistence,” the company aims to provide industry-leading products through comprehensive quality management, continuous improvement, and pursuit of zero defects.
Address: Sunye Electric Industrial Park, No. 669 Xinsheng Road, High-Tech Zone, Changsha City
Tel/Fax: 0731-89932666 0731-89932688
Business Phone: 400-0755-731
Technical Support: 400-0755-731
Recommended news
-

Guangzhou Rubber & Plastics Exhibition | Sunye ..
From June 9-11, the 2023 Guangzhou International Plastics, Rubber, and Packaging Printing Exhib..
-

Intelligence Converges in Central South China! ..
Crafting Professional Drive Solutions, Empowering Intelligent Equipment, Sunye Showcases Gener..
-

Born with the Same Core, Intelligent Motion Dri..
Currently, with the rapid advancement of intelligent manufacturing strategies across China, Hun..
-

With Our Original Mission, We Cross Mountains a..
Copytight © 2022 Changsha Sunye Electric Co., Ltd. All Rights Reserved湘ICP备2024064325号-1Business License InquirySitemap